⚡ The Gist
Indore Metro’s underground corridor records another significant milestone as the second Tunnel Boring Machine (TBM), named ‘Saraswati’, begins excavation between the Airport and Bada Ganpati.
The first TBM, ‘Narmada’, is already operational on the route and has completed approximately 100 metres of tunnel excavation. With Saraswati starting work on November 16, 2026, construction progresses on both underground tunnels.
The Story
The underground metro section requires two separate tunnels, one for trains travelling in each direction. Both tunnels are being constructed approximately 18 metres below ground level.
With two TBMs now operational, excavation progresses simultaneously on the underground alignment. The construction team also uses a locomotive engine and three trolleys to transport the excavated soil out of the tunnel, supporting the ongoing tunnelling work.
The project is preparing for the arrival of two more tunnel boring machines:
- TBM Kshipra: Expected to arrive in December 2026.
- TBM Avantika: Expected to reach Indore in January 2027.
Underground Metro Stations: Construction Progress
Work is also advancing at different stages across the underground stations:
- Airport Station: Excavation is almost complete, and base construction is underway.
- Ramchandra Nagar Station: Construction has reached an advanced stage.
- Regal Station: Around 130 of the planned 550 piling works are complete.
- Chhota Ganpati Station: Approximately 280 piles are planned. The station is being constructed at a depth of around 34–36 metres.
The simultaneous progress on tunnel excavation and underground station construction marks an important phase in Indore Metro’s underground development. The arrival of the remaining TBMs is expected to further expand excavation activity along the corridor.
🎙️ Indore Talk Take
Indore Metro’s underground section represents a major engineering challenge, requiring extensive excavation, specialised machinery and careful coordination beneath the city’s existing infrastructure.
With Saraswati joining Narmada, the project moves another step forward. However, the real measure of progress will be the timely completion of tunnels, stations, safety systems and supporting infrastructure.
Indore is building a metro beneath its streets. The question now is how efficiently this ambitious underground network moves from construction milestones to everyday public transport.